Virginia Department of TransportationAn official website of the Commonwealth of Virginia Here's how you knowAn official websiteHere's how you know

Route 7 corridor improvements

City/county: Fairfax County  

    Overview

    The Route 7 Corridor Improvements Project was celebrated with a ribbon cutting on May 22, 2024.

    Construction began in 2019 on the Route 7 Corridor Improvements Project aimed at enhancing safety, reducing congestion and expanding mobility for all users as part of Fairfax County’s Comprehensive Plan.

    The project widened Route 7 from four to six lanes between Reston Avenue and Jarrett Valley Drive. As a result, Route 7 is continuously at least six lanes from Leesburg to Tysons, a stretch totaling about 20 miles.

    The project also constructed shared-use paths on both sides of the entire seven-mile stretch of Route 7 between Reston Avenue and Jarrett Valley Drive. The shared-use paths tie into those on Route 7 beyond the eastern and western limits of the project, providing a direct bicyclist/pedestrian connection from the Fairfax County Parkway Trail to Tysons. The project also provided Gerry Connolly Cross County Trail users a new route under the rebuilt Difficult Run bridge to safely cross Route 7.

    The project additionally:

    • Constructed more than seven miles of noise barriers.
    • Improved access management at 19 intersections.
    • Reconstructed the Lewinsville Road intersection with the displaced left-turn lane from eastbound Route 7 to Lewinsville Road.
    • Built a new pedestrian underpass at Colvin Run Mill Park.

    Route 7 averages about 50,000 vehicles a day within the project limits.

    This project includes federal, state (including Smart Scale), Northern Virginia Transportation Authority and Fairfax County funds. The project was awarded to Shirley/Dewberry on July 18, 2018.

    Status: Recently complete

    Estimated start date: July 30, 2018

    Estimated completion date: May 2024

    Final design: Late Summer 2018 to Summer 2021

    Right of way: Early 2019 to Early 2021

    Utility relocation: Spring 2019 to Summer 2023

    Construction: Spring 2019 to Spring 2024

    Estimated cost of the project: $313.9 million

    • Preliminary engineering: $4.3 million
    • Right of way: $28.1 million
    • Construction: $281.5 million

    Route 7 Ribbon Cutting Ceremony - May 2024

    Six lanes on Route 7 open between Reston Avenue and the Dulles Toll Road - April 2024

    Final Noise Analysis Technical Report - November 2019 (Available Upon Request)

    Public Information Meeting - May 2019
    Brochure, Comment Sheet, Noise Wall Display, Right of Way Display, Presentation Slides, Map Exhibit 1, 2, 3, Ad

    Environmental Studies Document - April 2019

    Route 7 at Wolf Trap
    Route 7 Ribbon Cutting

     

    No videos currently available.

    Last updated: December 20, 2024

    Alert Icon

    Please note that this file is not ADA compliant. Choose one of below options: