Route 7 Corridor in Northern Virginia

News & Updates

Lane Closures & Traffic Alerts

Lane Closures for the Week of March 29 - April 4, 2020

Some lane closure hours along Route 7 between Reston Avenue and Jarrett Valley Drive have been temporarily extended due to decreased traffic. The project team will monitor traffic conditions and adjust lane closure hours as traffic conditions warrant. 

Crews will be performing storm pipe installation, excavation and fill operations, clearing and other construction-related activities during the daytime and overnight hours on March 29 - April 4 along eastbound and westbound Route 7, and on Reston Parkway. Please see details below.

Drivers are reminded that the speed limit along Route 7 has been temporarily reduced to 45 miles per hour in active work zones between Reston Avenue and Jarrett Valley Drive and Virginia law prohibits the use of handheld cell phones while driving through an active work zone.

During construction, drivers are asked to use caution and be alert to signs, flaggers and potential police direction in work zones. Slow-moving vehicles and equipment may be entering and exiting the road. Please see VDOT's video on navigating lane closure merges.

All work is subject to change based on weather and schedule. 

Please note that Washington Gas crews are also working along the corridor as part of the concurrent pipe replacement project

Find the latest information on travel conditions and work zones by visiting 511virginia.org or downloading the Virginia511 app. 

Upcoming Lane Closures

ROUTE 7 EASTBOUND

Between Reston Avenue and Jarrett Valley Drive
Monday, March 30 – Friday, April 3, 8 a.m. to 5 a.m.
Left or right lane closed for storm pipe installation, excavation, fill and clearing operations.

Between Baron Cameron Avenue and Jarrett Valley Drive
Sunday, March 29, 10 p.m. to Monday, March 30, 5 a.m.
Friday, April 3, 8 a.m. to Saturday, April 4, 9 a.m.
Saturday, April 4, 10 p.m. to Sunday, April 5, 8 a.m.
Left lane closed for median excavation. Night work hours may be subject to change based on traffic conditions. 

ROUTE 7 WESTBOUND

Between Jarrett Valley Drive and Reston Avenue
Monday, March 30 – Friday, April 3, 7 p.m. to 3 p.m.
Left or right lane closed for storm pipe installation, excavation, fill and clearing operations.

Between Jarrett Valley Drive and Baron Cameron Avenue
Sunday, March 29, 10 p.m. to Monday, March 30, 3 p.m.
Friday, April 3, 7 p.m. to Saturday, April 4, 9 a.m.
Saturday, April 4, 10 p.m. to Sunday, April 5, 8 a.m.
Left lane closed for median excavation. Night work hours may be subject to change based on traffic conditions.

RESTON PARKWAY NORTHBOUND

Between Fieldview Drive/Round Pebble Lane and Route 7
Monday, March 30 – Thursday, April 2, 9:30 a.m. to 3 p.m.
Friday, April 3, 9:30 a.m. to 2 p.m.
Left or right lane closed for fill operations.

RESTON PARKWAY SOUTHBOUND

Between Route 7 and Fieldview Drive/Round Pebble Lane
Monday, March 30 – Thursday, April 2, 9:30 a.m. to 3 p.m.
Friday, April 3, 9:30 a.m. to 2 p.m.
Left or right lane closed for fill operations.

Lane Closures for the Week of March 22-28, 2020

ROUTE 7 EASTBOUND

Between Reston Avenue and Jarrett Valley Drive
Monday, March 23 – Friday, March 27, 9:30 a.m. to 5 p.m.
Left or right lane closed for storm pipe installation, excavation, fill and clearing operations.

Between Baron Cameron Avenue and Jarrett Valley Drive
Sunday, March 22, 10 p.m. to Monday, March 23, 5 a.m.
Monday, March 23, 10 p.m. to Tuesday, March 24, 5 a.m.
Tuesday, March 24, 10 p.m. to Wednesday, March 25, 5 a.m.
Wednesday, March 25, 10 p.m. to Thursday, March 26, 5 a.m.
Thursday, March 26, 10 p.m. to Friday, March 27, 5 a.m.
Friday, March 27, 10 p.m. to Saturday, March 28, 9 a.m.
Saturday, March 28, 10 p.m. to Sunday, March 29, 8 a.m.
Left lane closed for median excavation and paving. Night work hours may be subject to change based on traffic conditions.

ROUTE 7 WESTBOUND

Between Jarrett Valley Drive and Reston Avenue
Monday, March 23 – Friday, March 27, 7:30 a.m. to 3 p.m.
Left or right lane closed for storm pipe installation, excavation, fill and clearing operations.

Between Jarrett Valley Drive and Baron Cameron Avenue
Sunday, March 22, 10 p.m. to Monday, March 23, 5 a.m.
Monday, March 23, 10 p.m. to Tuesday, March 24, 5 a.m.
Tuesday, March 24, 10 p.m. to Wednesday, March 25, 5 a.m.
Wednesday, March 25, 10 p.m. to Thursday, March 26, 5 a.m.
Thursday, March 26, 10 p.m. to Friday, March 27, 5 a.m.
Friday, March 27, 10 p.m. to Saturday, March 28, 9 a.m.
Saturday, March 28, 10 p.m. to Sunday, March 29, 8 a.m.
Left lane closed for median excavation and paving. Night work hours may be subject to change based on traffic conditions.

RESTON PARKWAY NORTHBOUND

Between Fieldview Drive/Round Pebble Lane and Route 7
Monday, March 23 – Thursday, March 26, 9:30 a.m. to 3 p.m.
Friday, March 27, 9:30 a.m. to 2 p.m.
Left or right lane closed for fill operations.

RESTON PARKWAY SOUTHBOUND

Between Route 7 and Fieldview Drive/Round Pebble Lane
Monday, March 23 – Thursday, March 26, 9:30 a.m. to 3 p.m.
Friday, March 27, 9:30 a.m. to 2 p.m.
Left or right lane closed for fill operations.

Reminder

Drivers on eastbound Route 7 turning right onto Baron Cameron Avenue must now yield to traffic from Springvale Road and traffic from westbound Route 7 turning left onto Baron Cameron Avenue.

Baron Cameron Yield     Baron Cameron Yield 2