Construction along Route 7

News & Updates

Project Updates Archives

Previous Construction Updates

July 2019

  • Utility relocation work continued near the Route 7/Baron Cameron Avenue intersection.
  • Completed shoulder widening on north side of westbound Route 7 west of Baron Cameron Avenue.
  • Installed temporary signals to accommodate upcoming traffic shifts at Reston Parkway, Utterback Store Road, and Baron Cameron Avenue.
  • Traffic was shifted slightly to the north on westbound Route 7 between Reston Avenue and Baron Cameron Avenue.
  • Began installation of barrier to protect the median work area west of Amanda Drive.
  • Continued earth moving operations west of Utterback Store Road.
  • Began storm sewer installation between Reston Avenue and Reston Parkway.
  • Click here to see photos.

June 2019

  • Started utility relocations near the Route 7/Baron Cameron Avenue intersection.
  • Completed grading and placement of stone for shoulder widening west of Utterback Store Road.
  • Installed concrete traffic barrier in the median west of Reston Parkway.
  • Removed topsoil from the median west of Utterback Store Road.
  • Began earth moving activities in the median west of Reston Parkway.
  • Began installing storm pipe and structures on the east side of the Reston Avenue intersection.
  • Relocated the pedestrian poles for the Utterback Store Road intersection.
  • Click here to see photos.