Construction along Route 7

News & Updates

Project Updates

Design Updates

  • Finalized Traffic Control Plans for the project area west of Baron Cameron Avenue. (April 2019)
  • Finalized Right-of-Way Plans. (August 2019)
  • Obtained two permits for the project area west of Delta Glen Court: The US Army Corps of Engineers State Programmatic General Permit and the Virginia Department of Environmental Quality (DEQ) Virginia Water Protection General Permit. (June 2019)
  • Published Public Notices for Virginia Marine Resources Commission (VMRC) (July 2019) and DEQ (August 2019) permits for the project area east of Delta Glen Court. 
  • 100% Roadway and Bridge Plans approved (October 2019).
  • Obtained two Clean Water Act permits for the project area east of Delta Glen Court: The US Army Corps of Engineers Individual Permit NOA-2014-01572 and the Virginia Department of Environmental Quality (DEQ) VWP Individual Permit 19-0554 (October 2019).
  • Obtained a modification of the VPDES Construction General Permit to cover the entire project area (October 2019).
  • The Virginia Marine Resources Commission (VMRC) issued the final permit for signature (October 2019).
  • Final noise analysis approved by Federal Highway Administration (FHWA) (November 2019).
  • Tabulated noise barrier votes from benefited parcels. All noise barriers that were deemed warranted, feasible, and reasonable in the Final Noise Analysis will be constructed with the project (April 2020). Click here for more information on the noise walls.

Construction Updates

April 2020Shoulder Widening

  • Difficult Run/Colvin Run area
    • Utility installation work
    • Paving and striping for the lane shift between Carpers Farm Way/Colvin Run Road and Serenity Woods Lane/Faulkner Drive
  • Installed storm sewer between Reston Avenue and Reston Parkway, and between Utterback Store Road and Carpers Farm Way.
  • Cleared and graded for a stormwater management pond west of Baron Cameron Avenue.
  • Relocated communications lines between Reston Parkway and Utterback Store Road.
  • Continued earth-moving operations between Reston Avenue and Riva Ridge Drive.
  • Performed fine grading for permanent pavement between Reston Parkway and Utterback Store Road.
  • Placed cement stabilization materials and concrete-treated aggregate, and installed underdrain between Baron Cameron Avenue and Carpers Farm Way.
  • Grading and stone placement for temporary pavement in the median between Faulkner Drive and Towlston Road
  • Strengthened shoulders and placed asphalt between Faulkner Drive and Towlston Road.
  • Click here to see photos.

March 2020Jack and Bore for Storm Sewer

  • Difficult Run/Colvin Run area
    • Preparatory work for utility installation
    • Median grading for temporary paving between Carpers Farm Way and Serenity Woods Lane.
  • Installed storm sewer between Reston Avenue and Carpers Farm Way.
  • Relocated and tied-in a water line between Reston Avenue and Reston Parkway.
  • A third-party communications utility was relocated between Reston Avenue and Reston Parkway.
  • Continued earth-moving operations between Reston Avenue and Carpers Farm Way.
  • Graded for temporary paving in the median between Serenity Woods Lane and Beulah Road.
  • Removed topsoil for temporary paving in the median between Beulah Road and Towlston Road.
  • Click here to see photos.

See project updates from previous months