News & Updates
Project Updates
Design Updates
- Finalized Traffic Control Plans for the project area west of Baron Cameron Avenue. (April 2019)
- Finalized Right-of-Way Plans. (August 2019)
- Obtained two permits for the project area west of Delta Glen Court: The US Army Corps of Engineers State Programmatic General Permit and the Virginia Department of Environmental Quality (DEQ) Virginia Water Protection General Permit. (June 2019)
- Published Public Notices for Virginia Marine Resources Commission (VMRC) (July 2019) and DEQ (August 2019) permits for the project area east of Delta Glen Court.
- 100% Roadway and Bridge Plans approved (October 2019).
- Obtained two Clean Water Act permits for the project area east of Delta Glen Court: The US Army Corps of Engineers Individual Permit NOA-2014-01572 and the Virginia Department of Environmental Quality (DEQ) VWP Individual Permit 19-0554 (October 2019).
- Obtained a modification of the VPDES Construction General Permit to cover the entire project area (October 2019).
- The Virginia Marine Resources Commission (VMRC) issued the final permit for signature (October 2019).
- Final noise analysis approved by Federal Highway Administration (FHWA) (November 2019).
- Tabulated noise barrier votes from benefited parcels. All noise barriers that were deemed warranted, feasible, and reasonable in the Final Noise Analysis will be constructed with the project (April 2020). Click here for more information on the noise walls.
Construction Updates
January 2021
- Continued noise barrier construction between Reston Avenue and Utterback Store Road.
- Storm sewer installation continued between Reston Avenue and Baron Cameron Avenue.
- Completed the north extension of the Piney Run box culvert.
- Removed existing asphalt between Baron Cameron Avenue and Colvin Run Road (east end).
- Shifted Carpers Farm Way traffic to the north in preparation for the installation of the new Colvin Run box culvert on the east side of Carpers Farm Way.
- Stage 2 construction pending right-of-way acquisition.
- Commenced the installation of the articulated block lining in the new Colvin Run channel.
- Continued earth-moving activities between Difficult Run and Faulkner Drive.
- Began excavation for the pedestrian tunnel under Route 7.
- Continued the water main relocation between Beulah Road and Towlston Road.
- Shifted traffic on eastbound Route 7 to the north between Lewinsville Road and Jarrett Valley Drive.
Click here to see January 2021 photos.
December 2020
- Continued noise barrier construction between Reston Avenue and Utterback Store Road.
- Storm sewer installation continued between Reston Avenue and Reston Parkway, and commenced between Utterback Store Road and Baron Cameron Avenue.
- Placed cement-treated aggregate and base asphalt between Reston Parkway and Utterback Store Road.
- Reconstructed and reopened the intersection of Route 7 and Great Passage Boulevard.
- Continued earth-moving operations between Baron Cameron Avenue and Carpers Farm Way.
- Finished cement-treated aggregate and base asphalt placement and completed curb and gutter along eastbound Route 7 between Baron Cameron Avenue and Carpers Farm Way.
- Stage 2 construction pending right-of-way acquisition.
- Continued earth-moving activities between Difficult Run and Faulkner Drive.
- Continued construction of the new channel for Colvin Run Stream.
- Continued storm sewer installation for Route 7 westbound lanes between Faulkner Drive and Trotting Horse Lane.
- Began relocating the water main between Beulah Road and Towlston Road.
- Completed asphalt placement and shifted traffic along westbound Route 7 between Lewinsville Road and Jarrett Valley Drive.