Route 7 Corridor in Northern Virginia

News & Updates

Traffic Alerts

Lane Closures for the Week of April 22-26, 2019

Crews will be performing utility location work during the daytime hours in several locations along eastbound and westbound Route 7 during the week of April 15-19, 2019. 

All work is subject to change based on weather and schedule. Please use caution and be alert to signs, as well as potential flagger or police direction in work zones. Slow-moving vehicles and equipment may be entering and exiting the road.

Please note that Washington Gas crews are also working behind barriers along the corridor as part of the concurrent pipe replacement project weekdays from 7 a.m. to 9 p.m. and weekends 9 a.m. to 9 p.m.

Find the latest information on travel conditions and work zones by visiting 511virginia.org or downloading the Virginia511 app.

ROUTE 7 EASTBOUND

Between Baron Cameron Avenue and Colvin Forest Drive
Monday, April 22 – Wednesday, April 24, 9:30 a.m. to 3 p.m.
Right lane closed for utility location activities.

Between Beulah Road and Towlston Road
Wednesday, April 24 - Thursday, April 25, 9:30 a.m. to 3 p.m.
Friday, April 26, 9:30 a.m. to 2 p.m.
Right lane and shoulder closed for utility location activities.

Between Georgetown Pike (Route 193) and Delta Glen Court
Monday, April 22 – Thursday, April 25, 9:30 a.m. to 3 p.m.
Friday, April 26, 9:30 a.m. to 2 p.m.
Right or left shoulder closed for temporary construction signage installation.

ROUTE 7 WESTBOUND

Between Towlston Road and Faulkner Drive
Wednesday, April 24 - Thursday, April 25, 9:30 a.m. to 3 p.m.
Friday, April 26, 9:30 a.m. to 2 p.m.
Left lane and shoulder closed for utility location activities.

Between Delta Glen Court and Georgetown Pike (Route 193)
Monday, April 22 – Thursday, April 25, 9:30 a.m. to 3 p.m.
Friday, April 26, 9:30 a.m. to 2 p.m.
Right or left shoulder closed for temporary construction signage installation.

Lane Closures for the Week of April 15-19, 2019

ROUTE 7 EASTBOUND

Between Colvin Run Road/Delta Glen Court and Middleton Ridge Road
Monday, April 15 - Thursday, April 18, 9:30 a.m. to 3 p.m.
Friday, April 19, 9:30 a.m. to 2 p.m.
Right lane and shoulder closed for utility location activities.

ROUTE 7 WESTBOUND

Between Colvin Run Road/Delta Glen Court and Georgetown Pike (Route 193)
Monday, April 15 - Wednesday, April 17, 9:30 a.m. to 3 p.m.
Right shoulder closed for temporary construction signage installation.

Between Middleton Ridge Road and Colvin Run Road/Carper’s Farm Way
Monday, April 15 - Tuesday, April 16, 9:30 a.m. to 3 p.m.
Thursday, April 18, 9:30 a.m. to 3 p.m.
Friday, April 19, 9:30 a.m. to 2 p.m.
Right lane and shoulder closed for utility location activities.

Between Middleton Ridge Road and Colvin Run Road/Carper’s Farm Way
Wednesday, April 18, 9:30 a.m. to 3 p.m.
Left lane and shoulder closed for utility location activities.